Has anyone found a way to get sketchy lines in just their own model and not the linked models?
Announcement
Collapse
No announcement yet.
Sketchy Lines in One Model Only
Collapse
X
-
Thank you Snowy and Jeff for your feedback. For 30% documents, I can't bring myself to not use Revit but my fittings are not set up well for coarse detail. Using sketchy for the MEP model, but standard for the linked arch model would solve my issue somewhat, but I'm not going to duplicate all my enlarged plans for this purpose.
As is common in many of these threads, the real issue is something entirely different and I'm trying to make people happy given their misunderstandings.
Comment
-
The PM/scope deliverable wanted one-line hand sketches. I'm faster and more nimble using Revit than hand sketching. Even at 30%, I think I can give a better product using Revit with more consistent data management for design (aka keep track of stuff).
There was concern over looking "too good" or something at 30%. Coarse detail could maybe have somewhat satisfied that, but as I mentioned, the fittings' coarse detail linework is not quite up to "good drafting practice" for single-line hand sketches. Therefore, proverbial rock and hard place.
I played with the sketchy line detail to consider making my work look less ...good(?)
I say let it eat, it looks good, let's move on. In a nutshell, I wanted my work to look 30%-ish. However, anyone that's done MEP knows that for a 30% construction estimate, you practically have to do 75% of your job. Same old story, different day, new attempt at dealing with it.
Comment
-
Originally posted by TFuller View PostI'm faster and more nimble using Revit than hand sketching.
Then follow that with the first (Revit) output and "But just in case not, here's something else that I think could work, which by the way took me considerably less time to produce"
Asking/expecting less fidelity? :crazy: WOW. #IfOnly.
Comment
-
Originally posted by snowyweston View PostModel it Revit, print it, trace it by hand, scan it, print that draft, spill some coffee on it then fax it to the PM with "I trust this is the kind of thing you were after?"...
Comment
-
Originally posted by snowyweston View PostModel it Revit, print it, trace it by hand, scan it, print that draft, spill some coffee on it then fax it to the PM with "I trust this is the kind of thing you were after?"...Jeff Hanson
Sr. Subject Matter Expert
Autodesk, Revit - User Experience
Comment
-
Originally posted by snowyweston View PostModel it Revit, print it, trace it by hand, scan it, print that draft, spill some coffee on it then fax it to the PM with "I trust this is the kind of thing you were after?"...
Then follow that with the first (Revit) output and "But just in case not, here's something else that I think could work, which by the way took me considerably less time to produce"
Asking/expecting less fidelity? :crazy: WOW. #IfOnly.
Comment
Related Topics
Collapse
-
I have a linked Revit MEP model in my project. The engineer has drawn some existing roof conditions with detail lines inside of the model. It has been...May 15, 2014, 05:28 PM
-
Hi guys, it's been a while since I've posted anything. Hopefully I get the same excellent help as I did before!
so I have an architectural...April 24, 2017, 05:35 PM -
hello all,
i am trying to plan to add lines for control joints between brick panels, metal panels etc. in elevation. i have a question regarding...June 3, 2011, 08:31 PM -
I have a linked Revit MEP model in my project. The engineer has drawn some existing roof conditions with detail lines inside of the model. It has been...May 15, 2014, 05:40 PM
-
I have a linked architectural model, which I have set to Linked View, with some custom adjustments to use as a for my structural plan. ...September 20, 2018, 01:48 PM