How to separate a revision schedule for the following format in a title block?
Announcement
Collapse
No announcement yet.
How to separate the revision schedule?
Collapse
X
-
Unfortunately it does not appear to be possible.
That's one of those things where I don't understand why the factory makes it work differently than other schedules. Normal schedules have a break symbol in the middle to make separate columns. Why couldn't the Revision Schedule have the same function available? Makes no sense to me.Last edited by PatrickGSR94; July 26, 2017, 03:18 PM.
Related Topics
Collapse
-
Good day everyone,
I need to ask if there's a possibility to Freeze The first field in the Revision Schedule usually showing Revision ( 0...February 2, 2015, 08:16 AM -
For my project, I have two (or more) revision clouds from two revision sequences on a sheet. Once I add the second could from a different revision, nothing...April 13, 2012, 02:41 PM
-
As per the title, is it possible to change the vertical alignment of entries in the revision schedule? My description is spanning multiple lines and everything...April 6, 2017, 12:55 AM
-
Hi Guys,
This might be a basic question but how do you delete the initial row on a new revision schedule?
I've attached two...August 19, 2015, 10:28 AM -
Can anyone advise me on revision schedules. I've added one to our title sheet which consists of a revision number, a date and a description.
...August 14, 2012, 10:22 AM