I have a multi-phase project for which I need to create a view that shows all of the demolition work across all phases. Initially it seemed that setting the Phase Filter for the view to "Show All" would work but it doesn't see multiple phases back in time.
Asking around the office I was given three possible solutions:
1) collapse all phases into two - existing and new
2) draw the demolished work in previous phases with drafting lines
3) stack a sequence of views, one per phase showing demo only, on top of a view showing only existing-to-remain at the latest phase
Based on my experience with room tags on demolition plans option 3 seems the most "Revity" way to go, but certainly comes with its own drawbacks.
Is there another, simpler way?
Chris
Asking around the office I was given three possible solutions:
1) collapse all phases into two - existing and new
2) draw the demolished work in previous phases with drafting lines
3) stack a sequence of views, one per phase showing demo only, on top of a view showing only existing-to-remain at the latest phase
Based on my experience with room tags on demolition plans option 3 seems the most "Revity" way to go, but certainly comes with its own drawbacks.
Is there another, simpler way?
Chris
Comment