I'm new to revit but have been learning vigorously the last 4 months. The trial by fire method.
I'm doing the electrical for a hotel type dwelling (military BEQ) with an associated community center building. My problem is that the electrical panels for the community building are fed from the main switchboard (MSB) in the BEQ and I need those loads to show on the MSB load schedule.
I'm pretty sure I cant bring one into the other. I've researched linking and binding.
Does anyone know of a workaround?