I have a curtain wall door that is on Level 1, and the base constraint of the curtain wall itself is set to Level 1. However, in my door schedule, it 's scheduling as if its on Level 2.
From what I've been able to dig up, I'm guessing that the curtain wall was originally drawn on Level 2, then changed at some point to Level 1, which is why the door is scheduling on 2.
Is there any way to remedy this situation aside from deleting and redrawing the curtain wall (which I don't want to do at this point)? I've tried switching the panels in and out with no success.
From what I've been able to dig up, I'm guessing that the curtain wall was originally drawn on Level 2, then changed at some point to Level 1, which is why the door is scheduling on 2.
Is there any way to remedy this situation aside from deleting and redrawing the curtain wall (which I don't want to do at this point)? I've tried switching the panels in and out with no success.