As per our project requirement we have placed drainage pipes
with 1% slope.we have set 1% slope for the placement of drainage pipe but the slope of pipes are changed when placed pipe fittings on pipe.
Is there any option to lock slope or to toplace fittings inlign with pipe?
Thank you
Regards
Swapnil
with 1% slope.we have set 1% slope for the placement of drainage pipe but the slope of pipes are changed when placed pipe fittings on pipe.
Is there any option to lock slope or to toplace fittings inlign with pipe?
Thank you
Regards
Swapnil
Comment