    It's great that you can 'bound layer above' with a structural deck, but the volume takeoff of the layer above doesn't subtract out the deck flutes for you. What's the best practice for automating a correct takeoff with the area below the deck flutes excluded?
    Last edited by cbaze; August 3, 2011, 09:36 PM.

    #2
    I would use a formula to take out the conc below the deck. Do a little math to find the magic number then its a simple

    Total Conc Volume * % = Volume with deck removed.
    -Alex Cunningham

    Comment


      #3
      Yes, but that percentage would change based on the thickness of the slab. It seems to me that it would be easier to subtract a number from the thickness of the slab then multiply by the area. That way one deck profile = only one number to deal with. Has anyone taken the time to modify the OOTB deck profile to parametrically calculate what number you should subtract from the thickness of the slab?

      -Chris

      Comment


        #4
        Anyway it works for you. But the solution for your problem will be useing a calculated formula in the schedule will get you what you are looking for.
        -Alex Cunningham