    Does anyone know how to set up a schedule show it shows tags or miscellaneous graphics?

    Two examples:

    1. Door Schedule - Show the actual door tag in the first column of the schedule w/ the "mark" parameter nested within the tag.

    2. Fixture Schedule - Set up a cell in the schedule that shows a plan view of each fixture family.

    #2
    Neither can be done in a native Revit Schedule. The former, i dont see a real need for, besides appeasing old graphics standards (and even then, none of the offices i was in ever did it), and the latter ive heard asked for a number of times, but unfortunately there isnt a way to do it.

    Since the cell spacing in a schedule doesnt change unless the lines wrap, you COULD (if you want a really UGLY solution, and i still think its not value adding), array a detail line down the sheet to do the former. The latter... You need a Legend view, seperate from the schedule.
    Aaron "selfish AND petulant" Maller |P A R A L L A X T E A M | Practice Technology Implementation