Thread: Phases

  1. #1
    Member
    Join Date
    February 9, 2018
    Location
    Va Beach, VA
    Posts
    59
    Current Local Time
    03:52 PM

    Phases

    I have a project coming up where I am sure "Phases" would be helpful.
    I have studied quite a few movies and other but don't understand very much.
    I will be drawing the original floor plan, foundation and roof of a one story home.
    From there we will be redesigning most everything- the footprint will be enlarged., foundation, walls moved/added and the roof will probably be a whole new configuration. Keeping it one story.
    I'm wondering if after I get the original drawn, if there is something i could do to set my original? Like maybe highlight everything and click phase?
    I certainly understand that it may take me a long while before I fully understand phases, but I thought this a good project to start learning.
    I will be renaming the file at the point I have the original built/drawn, but I know there are better ways.
    Any help will be appreciated.
    Thanks!
    Gary

  2. #2
    BIM there, done that cliff collins's Avatar
    Join Date
    December 14, 2010
    Location
    St. Louis, MO
    Posts
    1,913
    Current Local Time
    10:52 AM
    Here is a good place to start:
    https://knowledge.autodesk.com/suppo...429E5-htm.html

    Existing House: On Existing Phase
    New Construction: on New Construction Phase
    Demo: Demolish existing items on New Construction Phase
    kowen1208 likes this.

  3. #3
    Moderator DaveP's Avatar
    Join Date
    January 10, 2011
    Location
    St Paul, MN
    Posts
    2,648
    Current Local Time
    10:52 AM
    One other important point with Phases:
    You CANNOT move items and have them remain where they were in the previous Phase.
    You can get things to show up or not in different Phases, but there is only ONE location for an element.

    You mention Walls "moved."
    Think of what happens when they do the remodel.
    They do not just shove the existing Wall into a new location.
    The builders tear down the existing wall and build a new one in the new location.
    That's exactly what you need to do in your Revit model.
    kowen1208 and Ning Zhou like this.

  4. #4
    Member kowen1208's Avatar
    Join Date
    January 18, 2013
    Location
    Utah
    Posts
    354
    Current Local Time
    09:52 AM
    Before you model anything, I'd set up views with the following phasing and phase filters:

    Phase: Existing
    Phase Filter: Show New

    Phase:New Construction
    Phase Filter: Show Previous and Demo

    Phase: New Construction
    Phase Filter: Show Previous and New

    Some other things to be aware of:
    If a host element is demolished, all elements hosted to it will be demolished.
    Existing walls to remain will try to join with demolished and new walls alike. When I do multi-phase projects, I disallow wall joins on all my loose walls ends.
    cganiere and Ning Zhou like this.

  5. #5
    Member
    Join Date
    January 19, 2012
    Posts
    246
    Current Local Time
    10:52 AM
    I just had the most unique case of where the gyp gets Demoed & "Stud to Remain" to get a new layer in its place. Thankfully it's a small 10K SF project. I just Duplicated a Partition with an infill for the Stud layer to indicate "Existing Stud w New Gyp" than to model the Layers individually (because things can & have always changed in a project). My question is for in the case of a large project where this has happened. What strategies have been successfully used or should have been used reflecting back?

  6. #6
    Member
    Join Date
    May 18, 2011
    Location
    Calgary, AB
    Posts
    345
    Current Local Time
    09:52 AM
    Quote Originally Posted by cftrevizo View Post
    I just had the most unique case of where the gyp gets Demoed & "Stud to Remain" to get a new layer in its place. Thankfully it's a small 10K SF project. I just Duplicated a Partition with an infill for the Stud layer to indicate "Existing Stud w New Gyp" than to model the Layers individually (because things can & have always changed in a project). My question is for in the case of a large project where this has happened. What strategies have been successfully used or should have been used reflecting back?
    I did one just like that not to recently. Unfortunately the project was moving too fast that we couldn't capture that level of information, so we ended up showing the final design location of walls and it was up to the contractor to decide if the studs exist and just adding gyp brd or if they had to construct a new wall. Yes, it was an absolute nightmare.

    I think the only way would be to model the studs and the gyp brd on either side separately. Then you can demo the gyp brd and then show new gyp brd. Then you can tag them appropriately.

  7. #7
    Member Knitro87's Avatar
    Join Date
    December 3, 2014
    Location
    Austin, TX
    Posts
    267
    Current Local Time
    10:52 AM
    You CAN have a demo phase, but for Pete's sake, do NOT call it "Demo". That is, unless, you want to feel great vengeance and furious anger from RFO members. Instead, call it Phase 1 (or Phase A). New Construction can be done on Phase 2 (or Phase B). You're welcome!

  8. #8
    Member kowen1208's Avatar
    Join Date
    January 18, 2013
    Location
    Utah
    Posts
    354
    Current Local Time
    09:52 AM
    Quote Originally Posted by Knitro87 View Post
    You CAN have a demo phase, but for Pete's sake, do NOT call it "Demo". That is, unless, you want to feel great vengeance and furious anger from RFO members. Instead, call it Phase 1 (or Phase A). New Construction can be done on Phase 2 (or Phase B). You're welcome!
    Are there any specific benefits to breaking the demolition out into its own phase? And any specific reasons for not calling the phase "demo"?

  9. #9
    Member Knitro87's Avatar
    Join Date
    December 3, 2014
    Location
    Austin, TX
    Posts
    267
    Current Local Time
    10:52 AM
    Quote Originally Posted by kowen1208 View Post
    Are there any specific benefits to breaking the demolition out into its own phase? And any specific reasons for not calling the phase "demo"?
    If demolition plans need to show new and/or temporary elements that are not related to the "New Construction" scope, separate phases would have to be created. It's typically a bad idea to call it "Demolition Phase" because that's not the only thing happening on the plans.
    Last edited by Knitro87; May 22nd, 2018 at 08:56 PM.
    kowen1208 and Ning Zhou like this.

  10. #10
    Forum Co-Founder Twiceroadsfool's Avatar
    Join Date
    December 7, 2010
    Location
    Dallas, TX
    Posts
    9,457
    Current Local Time
    10:52 AM
    For what its worth, i would never call a phase *New Construction,* either. Autodesk names them that OOTB, which is ridiculous. Its only New, until it isnt. And it isnt always Construction, when its Demolition. My Phases are simply called Existing, Phase 1, Phase 2, and so on.
    Knitro87 and kowen1208 like this.

Page 1 of 3 123 LastLast

Similar Threads

  1. Working with phases !!
    By ahmed_hassan in forum Architecture and General Revit Questions
    Replies: 4
    Last Post: July 2nd, 2012, 12:09 AM
  2. 3D dwf with phases overrides
    By redmonki in forum Architecture and General Revit Questions
    Replies: 0
    Last Post: March 14th, 2012, 09:14 AM
  3. Phases...
    By Dave Jones in forum Out There
    Replies: 5
    Last Post: September 20th, 2011, 07:06 PM
  4. Famille électricité 2 phases ou 3 phases
    By amigost in forum MEP - Family Creation
    Replies: 1
    Last Post: May 15th, 2011, 12:26 PM
  5. Phases
    By gdoherty0102 in forum Architecture and General Revit Questions
    Replies: 20
    Last Post: March 15th, 2011, 07:28 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •